The best time to discover that a shower valve is backordered or a refrigerator won’t fit the cabinet opening is while the room is still usable. In our Design + Build process, we identify the selections that affect measurements, plumbing, electrical work, and trade sequencing before scheduling demolition.
Kitchen decisions to make early
- Cabinetry: Approve the layout and cabinet sizes before production. Verify delivery, storage, and how the installation will be staged.
- Appliances: Confirm model numbers and check the specifications for clearances, utility connections, and ventilation. A different model can affect the cabinet opening or utility locations.
- Countertops and tile: Choose the material and check availability early. Countertops are often measured for fabrication after the cabinets are installed, so the plan should allow for that sequence.
Bathroom decisions to make early
- Shower valves and trim: Confirm the rough-in valve matches the trim and is available when the plumber needs it.
- Tile and stone: Verify quantities and check the delivery for damage or visible differences before installation is scheduled.
- Vanity, lighting, and fixtures: Confirm dimensions and mounting details early enough for plumbing, wiring, or wall support to be placed correctly.
What if something is late?
First, find out which work depends on the missing item and whether anything else can safely move ahead. Then review the choices: wait for the preferred product, approve a substitute that fits the design and technical requirements, or adjust the start date. Confirm the effect on cost and schedule before ordering a substitute.
Key items may need to be on site before demolition. Others only need a confirmed delivery date tied to installation. We also plan where to store materials and who will check the cartons, model numbers, quantities, and condition when they arrive.